Key Project Details
Client: Spencer
Start date: 1st February 2014
End date: 1st February 2015
Duration: 52 weeks
Value: £1.5m
Location: Sandy, Cambridgeshire
Client: Spencer
Start date: 1st February 2014
End date: 1st February 2015
Duration: 52 weeks
Value: £1.5m
Location: Sandy, Cambridgeshire
The platform extensions at Sandy were the key part of the Outer Thameslink Platform Lengthening Programme. Aaron Rail was commissioned by Spencer to construct additional platform length to accommodate the large number of commuters to London. This needed to be long enough for 12-car trains.
The construction of the 2 platform extensions took place over a 12-month period around commissioning of the rail systems assets. Each platform was extended by 75m to allow the use of 12 car trains by the TOC’s and increase passenger capacity into London from the East Coast Main Line.
Aaron Rail was procured to complete the following works:
In addition to the above Aaron Rail also assisted with the completion of the following works:
The improvements were a significant milestone in the delivery of the Thames Link Outer platform extension programme.
Minum am aces repro explitatur, quis mo mo eos doles dest voluptas consequi totas et adita volessi di rehent enimi, sint am que elestot aerumque lab ium harum nonsedi gnatur re dus as archiliquam alis maionsed quunto cum sunt quasitae verum estiissu
Copyright Aaron Group 2021, All Rights Reserved.
Aaron Rail Limited, Registered in England and Wales, Number 08454101